Tulasi Lake Front,block 9

TULASI CONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200002519

TULASI LAKE FRONT,BLOCK 9 is a residential apartment project in SURARAM VILLAGE-1 / Suraram, Qutballapur mandal, Medchal-Malkajgiri district, developed by registered promoter TULASI CONSTRUCTIONS. The filed site extent is 668.9 sq. m total and 668.90 sq. m net; the project records one building with 1 Stilt + 5 upper floors and 15 apartments. The apartments comprise 5 2BHK and 10 3BHK homes. Its TG-RERA registration is P02200002519, registered from 01/02/2021 to 30/07/2026, and the permit records completion before 30 July, 2026.

More from Tulasi Constructions · 7 projects →

01What we found

Period endedTG-RERA registration ran to 30 Jul 2026 - check its extension on TG-RERA
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
13items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

13 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameTULASI LAKE FRONT,BLOCK 9 RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionBlock 9; phase boundaries or a separate phase description are not disclosed in the available record. RERA record
TG-RERA registrationP02200002519; registered from 01/02/2021 to 30/07/2026. The certificate states five years and says registration may be extended by the Authority; no extension is recorded in the supplied certificate.
Registered promoterTULASI CONSTRUCTIONS, identified as a partnership in the RERA promoter information. RERA filing Corporate record
RERA statusThe registration certificate records the project registration. Its stated validity ended 30/07/2026; a current post-expiry status is not established by the supplied record.

Land and geographic identity

FieldRecord
Locality / revenue villageSURARAM VILLAGE-1 / Suraram, as recorded in the project filing and supporting project documents. RERA record RERA filing
MandalQutballapur RERA record
DistrictMedchal-Malkajgiri RERA record
PIN500015 RERA record
Project survey numbers96/A, 97 and 98 RERA filing
Cadastral recordBhu Bharati data lists survey 96/అ (whole-survey match; 5.02 acres-guntas) and subdivisions under 97 and 98. The RERA filing does not identify which of the listed subdivisions under 97 and 98 are held for the project. Cadastral map
Site extent668.9 sq. m total and 668.90 sq. m net, as filed; the building-permit extract also states 668.9 m2. RERA filing
Road widening / FTL / nala affected area00 sq. m in the RERA land details; the building-permit extract records road-affected and nala-affected area as 0. RERA filing
BoundariesEast: PLOT NO 9; west: ROAD WIDTH-12; north and south: VACANT LAND. RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building-permit approval2/C26/08255/2020, approved 30 July, 2020. Approvals record
Building configuration in permit1 Stilt + 5 upper floors; stated height 14.85 m.
Approved area figuresRERA filing states approved built-up area of 1966.11 sq. m. The permit extract separately lists residential upper-floor area of 1,792.50 m2 and stilt parking area of 359.50 m2. These are distinct filed figures. RERA filing
Buildings / blocksOne building is recorded in the RERA land details; the permit identifies Building - A-1. RERA filing
Units1 building unit is recorded in the land-details fields; RERA unit records list 15 apartments. RERA filing RERA unit table
Parking levels / provisionStilt parking is part of the permit configuration. The permit says the approved cellar and stilt parking areas are to be used exclusively for vehicle parking; the supplied permit extract specifies a stilt parking area of 359.50 m2. No parking-space count is supplied.

Offering and status

FieldRecord
Configurations2BHK and 3BHK RERA unit table
RERA-filed unit counts5 2BHK and 10 3BHK; 15 total RERA unit table
Booked / availableThe portal-derived record shows 0 booked and 5 available 2BHK; 0 booked and 10 available 3BHK. These counts are indicative: the supplied record gives no as-of date for the booking data. RERA unit table RERA unit details
RERA-filed saleable area1149.0 for 2BHK and 1365.0 for 3BHK, as recorded in the supplied RERA unit data; the unit record does not provide a measurement unit label for these figures. RERA unit details
Construction stageNo independently verified current construction-stage assessment is supplied. The RERA amenities record lists progress as 0% for its listed items; this is not a site inspection. RERA amenities
Completion deadlineThe permit records completion before 30 July, 2026; the RERA certificate also records validity ending 30/07/2026. Registration validity and the stated construction deadline are separate matters.
Occupancy-certificate statusA GHMC occupancy certificate, 0100/GHMC/KPL/2022-OC, dated 07 February, 2022, is supplied for a residential building at Plot Nos. 71, 72, 79 and 80, Surveys 96/A, 97 and 98. Its project-phase/block scope is not expressly matched to “BLOCK 9” in the certificate extract.

2. The project story

A GHMC occupancy certificate dated 07 February, 2022 is among the supplied project documents. It covers a residential building on the same stated survey numbers and plot numbers, but the certificate extract does not expressly identify its scope as this named Block 9 registration. The certificate is therefore described here as a supplied record, not as confirmation that all units or common facilities in this registration are occupancy-certified.

3. Master plan, architecture & building design

The permit extract records 13 rainwater-harvesting structures, 30 trees, space for a transformer, a garbage house within the premises and an ETP. It records a tot-lot area of 0 m2. The extract does not provide a site plan or floor-plan measurements sufficient to describe flat-per-floor arrangement, footprint, lifts, stairs, entry/exit design, internal circulation, landscaping layout or residential/common-area distribution.

The supplied floor-plan dataset reports one drawing, but no measured drawings; it records no_flats: 1. No software-measured carpet area or room dimensions are available. Floor plans

4. Homes, configurations & floor plans

The RERA unit record lists 15 apartments across two configurations. The filed saleable-area figures below are reproduced as recorded; the supplied unit data does not label their measurement unit. RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK5051149.0Not available: no drawing-based measurement suppliedNot supplied
3BHK100101365.0Not available: no drawing-based measurement suppliedNot supplied

Booking and availability figures are indicative because the supplied portal-derived record has no as-of date. RERA unit table RERA unit details

No software-measured carpet area, room dimensions, balcony or utility measurements are supplied. The floor-plan dataset notes that carpet area measured from drawings would be a software measurement rather than a RERA disclosure, and that RERA saleable area includes a share of common areas; no such drawing measurement is available for this project in the supplied data. Floor plans

5. Parking & vehicle circulation

The vendor record lists open and closed car parking, but does not provide quantities or establish sanctioned provision or unit-specific allocation. Promoter website

6. Amenities, recreation & open spaces

The GHMC permit extract records specified site provisions. The RERA portal amenities record separately lists items and shows 0% progress for the listed entries; this is not independent verification of on-site completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot0 m2 in permit extractGHMC building permitNo separate completion verification supplied
Trees30 treesGHMC building permitNo separate completion verification supplied
Community buildingsNo size or facility detail suppliedRERA amenities record RERA amenities0% recorded
Aggregate recreational open spaceNo area suppliedRERA amenities record RERA amenities0% recorded

The vendor lists security and parking among its claimed amenities, but supplies no facility sizes, quantities, or evidence of completion. Promoter website

7. Utilities, building services & safety

The permit extract records an ETP, rainwater-harvesting requirements, space for a transformer and a garbage house within the premises. It also requires a fire NOC from the Director (EV&DM) before issue of an occupancy certificate. These are permit-recorded provisions or conditions, not confirmation that the systems are installed, operational or currently cleared.

ServiceSupplied evidence
WaterRERA amenities record marks Water Supply: YES, with 0% progress; the vendor lists 24x7 water supply. No source, storage or treatment capacity is supplied. RERA amenities Promoter website
Sewerage / drainageThe RERA record lists sewerage, storm-water drains, and treatment and disposal of sewage and sullage water, each at 0% progress. The permit extract requires an ETP. No capacity or completion evidence is supplied. RERA amenities
ElectricalPermit requires space for a transformer; the RERA record marks electrical meter room, sub-station and receiving station YES, at 0% progress. No electrical capacity or backup specification is supplied in the RERA record. RERA amenities
Rainwater harvestingPermit lists 13 RWHPs; RERA record marks water conservation/rainwater harvesting YES, at 0% progress. RERA amenities
Fire and life safetyRERA record marks fire protection and fire safety requirements YES, at 0% progress. Permit requires an occupancy fire NOC before issue of an occupancy certificate. No specific equipment, escape-stair details or current clearance evidence is supplied. RERA amenities
WastePermit records a garbage house within the premises; the RERA record lists solid-waste management and disposal at 0% progress. RERA amenities
Lifts, accessibility and securityNo project-specific lift, accessible-circulation or security-system details are supplied in the RERA documents. The vendor lists security, without technical particulars. Promoter website

8. Location, access & connectivity

The supplied location record lists Financial District (Nanakramguda), 1.2 km as an anchor, but provides no measurement method or route context. Location record No official public-transport or landmark-distance details are supplied in the project location record.

9. Developer & development status

The registered promoter is TULASI CONSTRUCTIONS, identified in the RERA promoter information as a Partnership. Its supplied GSTIN is 36AAOFT0091L1ZQ. The RERA address record identifies GANESH PLAZA, GANESH NAGAR, SURARAM VILLAGE, SURARAM VILLAGE-1, Qutballapur, Medchal-Malkajgiri, 500015. RERA filing Corporate record Parties record

The registration certificate separately gives the promoter office as Village: Quthbullapur-1, Mandal: Qutballapur, District: Medchal-Malkajgiri, Pin: 500054.

Boddu Ashok is identified in the supplied Form B as an authorised signatory representing Tulasi Constructions; the declaration states a completion period ending 30/07/ followed by a corrupted year (“a026”), so the year in that particular declaration is not legible with confidence.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02200002519, issued 01/02/2021; validity stated through 30/07/2026
Scope and noteRegistration for TULASI LAKE FRONT,BLOCK 9; identifies Surveys 96/A, 97 and 98 and Plot Nos. 71, 72, 79 and 80.
GHMC building permit order
Identifier / dateApproval 2/C26/08255/2020, dated 30 July, 2020; file no. 2/C26/11464/2018
Scope and noteResidential Building A-1; 1 Stilt + 5 upper floors.
GHMC occupancy certificate
Identifier / date0100/GHMC/KPL/2022-OC, dated 07 February, 2022; application 000462/GHMC/0233/KPL2/2022-OC
Scope and noteExtract records a residential building on Plot Nos. 71, 72, 79 and 80, Surveys 96/A, 97 and 98, and says it is fit for occupation. Its scope is not expressly matched to Block 9 in the supplied extract.
RERA Form B declaration
Identifier / dateDated 0 / 01. /2021
Scope and notePromoter declaration by Boddu Ashok, representing Tulasi Constructions, concerning title basis, encumbrance disclosure and regulatory undertakings.
Land title search report
Identifier / dateAdvocate’s report, document 146190
Scope and noteConcerns the scheduled property in Surveys 96/A, 97 and 98, Suraram village.
Sale deed in title file
Identifier / dateDocument no. 6989/2020, dated 17 March 2020
Scope and noteFiled title material describes 800.0 square yards or 668.8 square metres in Surveys 96/A, 97 and 98.
Filed agreement-for-sale template
Identifier / dateDocument 139379
Scope and noteTelangana RERA-form template with project and allottee particulars left unfilled; it does not establish execution of a unit-specific agreement.

The supplied evidence does not include an extracted approved layout drawing or floor-plan geometry suitable for describing internal layout or unit room dimensions. Document index Floor plans

Other registrations of Tulasi Lake Front

Frequently asked questions

Is TULASI LAKE FRONT,BLOCK 9 registered with Telangana RERA?

Yes. TULASI LAKE FRONT,BLOCK 9 is registered with the Telangana Real Estate Regulatory Authority as P02200002519; the registration status is New Project.

Who is the developer of TULASI LAKE FRONT,BLOCK 9?

The promoter named in the RERA registration is TULASI CONSTRUCTIONS.

Where is TULASI LAKE FRONT,BLOCK 9 located?

TULASI LAKE FRONT,BLOCK 9 is in SURARAM VILLAGE-1, Qutballapur, Medchal-Malkajgiri, Telangana (500015).

When will TULASI LAKE FRONT,BLOCK 9 be completed?

The promoter's proposed date of completion filed with RERA is 30/07/2026. This is the promoter's declaration, not a guarantee.